LOL Supports Competitive Bidding Process for Renewable Energy

by | Mar 23, 2026 | Health & Safety, News & Blog

The Competitive Bidding Framework was adopted by the Hawaii Public Utilities Commission in December 2006 and updated in 2022. This established a competitive process for acquiring or building new energy generation sources in Hawaii. Life of the Land asserts that this is critical to minimize costs for ratepayers.

 

A waiver mechanism was often used in the early years as there was a lack of cost-effective alternatives. Hu Honua received a waiver from competitive bidding in 2008 and the Na Pua Makani (Kahuku Wind Farm) in 2014. In recent years no waiver has been granted.

 

The PUC informed the House Energy and Environmental Policy Committee last week that they oppose waivers from the competitive bidding process.

 

Standing beside PUC Chair Jon Itomura, PUC utility analyst Daniel Park stated, “We’re very confident that as long as we continue to utilize this framework that we have in place, we’re going to keep generation costs as low as possible for our ratepayers.”

 

Mark Glick has a long history in the gas sector. He is seeking to overturn existing policies and practices..

 

“Mark Glick, head of the Hawaii State Energy Office, asked the state Public Utilities Commission in a March 9 letter to hold off making a decision on the renewable- energy project by Hawaiian Electric and consider new information on alternatives that Glick suggested would include a proposal by a Japanese company to generate more electricity at a “materially lower cost” for ratepayers.” ‘Backroom deal’ meddling alleged in power plant case by Andrew Gomes, Hawaii Star-Advertiser, March 22, 2026. “Glick also said the PUC can consider unsolicited proposals outside its competitive bidding framework and that such consideration is warranted.”

 

The PUC received letters in favor of maintaining the competitive bidding process from Hawaiian Electric Company, Representative Nicole Lowen, Gerald Sumida, Life of the Land, Earthjustice, IBEW Local 1260, Hawaii Farm Bureau, Edison Electric Institute, PAR Hawaii, AES, Ameresco, and Harbert Management Corporation (Kalaeloa Partners and Hamakua Energy). Comments were also filed by Tony Baldomero, the former Associate Director of the Hawaii Campaign Spending Commission

 

Representative Nicole Lowen

 

Dear Chair Itomura and Commissioners:

 

I am writing in my capacity as Chair of the House Committee on Energy and Environmental Protection to express serious concerns regarding the March 9, 2026 letter submitted by the Hawai’i State Energy Office (HSEO) in the above-referenced docket.

 

HSEO is requesting an eleventh-hour delay of a decision on a project that has undergone years of planning, analysis, and procurement pursuant to the framework established by the Commission. Such a delay risks undermining significant prior work, introducing uncertainty into the regulatory process, and may ultimately increase costs to ratepayers while jeopardizing electric system reliability.

 

If decision-making is delayed based upon the reasoning offered by HSEO, it would seriously undermine the integrity of the Hawai’i’s competitive renewable energy procurement process. This process depends on market confidence that procurements will be conducted under established rules, bids will be evaluated consistently, and outcomes will not later be reopened or destabilized through last-minute challenges. Weakening that confidence reduces credibility, increases risk for developers, and would raise costs and discourage participation, making the entire process less effective. A fair and predictable procurement process is necessary for ensuring the best deal for ratepayers.

 

The justification offered by HSEO also appears to rely heavily on the speculative possibility of an alternative project. Specifically, HSEO references a “public proposal for additional firm generation capacity on O’ahu proposing to deliver up to 500 MW of firm capacity at materially lower cost to ratepayers.” However, no such proposal has been submitted to the Commission or made available to the public, no verifiable cost data has been provided, and there is no evidence to substantiate or reasonably evaluate the claims of faster timelines and lower costs. It is deeply concerning to suggest that a duly conducted procurement process should be set aside based on an unvetted and non-transparent alternative.

 

I am also deeply concerned by the timing and context of HSEO’s request. At a recent informational briefing before the House Committee on Energy and Environmental Protection on March 12, significant questions were raised regarding the analytical foundation of HSEO’s Alternative Fuels, Repowering, and Energy Transition Study, including identifying material errors affecting cost conclusions in the study that have been used broadly by HSEO to support and socialize the suggested “alternative proposal.” It is troubling that the same body now seeks to influence an active Commission proceeding in a manner that would advantage a specific, non-competing entity.

 

Taken together, these actions raise legitimate questions about whether the request is grounded in a commitment to energy affordability, system reliability, decarbonization, and other core directives of the office, or whether it reflects an effort to advance a particular outcome outside of established regulatory processes, for purposes other than the public interest.

 

The Commission’s role in maintaining a fair, transparent, and reliable energy system is critical. I respectfully urge the Commission to carefully consider the broader implications of HSEO’s request—not only for this docket, but for the perceived integrity of Hawai’i’s energy procurement process and the Commission’s decisions going forward.

 

Thank you for your attention to this matter.

 

#      #      #